What “post-EEG” actually means

Under the EEG (Germany's Renewable Energy Sources Act), turbines receive a fixed feed-in tariff for 20 years, counted from commissioning plus the remainder of the commissioning year. After that, the entitlement ends. The turbine may keep running, but its power has to be sold another way.

The first large cohorts of German wind turbines passed this point long ago. Most of them are in the 500 kW to 1.5 MW class and are often in good technical shape. Without a fixed tariff, the economics become the deciding question.

03

The four options

In practice, there are four paths. Which one pays off depends on the site, the turbine's condition, and the lease and zoning situation.

  • Continued operation with direct marketing: requires a lifetime extension assessment and only pays off when operating costs are low.
  • Selling the turbine: operations pass to the buyer with all obligations, including the decommissioning obligation.
  • Repowering: replacement with a modern turbine, usually under the simplified procedure of § 16b BImSchG (Federal Immission Control Act).
  • Decommissioning: complete removal of the turbine and restoration of the land, funded from the posted security.

04

The lifetime extension assessment

To run a turbine beyond its design life, insurers and authorities usually require an assessment based on the DIBt guideline (German Institute for Building Technology) or the principles of the BWE guideline (German Wind Energy Association). It examines the support structure, fatigue and the condition of the main components.

The assessment determines how long continued operation is permitted and which inspection intervals apply from then on. If the result is negative, continued operation ends.

05

Who carries the decommissioning obligation

The obligation to decommission lies with the operator and is usually secured by a bank guarantee or other security posted with the permitting authority. It remains in force even if the turbine is idle, until the turbine is removed or the obligation is validly transferred.

In a sale, this point is central. If the buyer takes over the decommissioning obligation together with the security, the seller is fully released. Without that arrangement, the seller keeps a risk that lowers the purchase price.

06Data sheet

Frequently asked questions

Does a turbine automatically have to shut down after 20 years?

No. Only the fixed EEG tariff ends. The permit remains valid, and continued operation is allowed with a positive assessment.

Does continued operation pay off without the tariff?

That depends on site quality, operating costs and power prices. Turbines with high maintenance costs often no longer pay off under direct marketing.

Can I still sell a turbine that's not running?

Usually, yes. The valuation is based on location, condition and zoning status. Whether the turbine is currently generating power matters less.