Repowering under § 16b BImSchG: How the process works
When an old turbine is replaced, the authority reviews only the changes compared with what's already there. This article covers what § 16b simplifies, which reviews remain, and where projects stall.
7 min read
02
The core idea of § 16b
§ 16b of the BImSchG (Germany's Federal Immission Control Act) governs the procedure for replacing existing wind turbines. The authority reviews the changes compared with the permitted existing installation.
If the new turbine has a smaller impact than the old one on a given point, such as noise or shadow flicker, that point doesn't need to be reassessed. This shortens the process. The substantive requirements still apply.
03
What still gets reviewed
The relief applies to the scope of review. The protected interests stay the same. The following typically need to be addressed:
- Species protection: modern turbines are taller, which changes the impact on breeding and migratory birds and on bats.
- Noise and shadow flicker: must be reassessed if hub height or rotor diameter increase significantly.
- Zoning law: height limits in land-use or development plans still apply.
- Grid connection: the higher output needs a new commitment from the grid operator.
04
A typical project timeline
The project starts with a site and feasibility analysis. It establishes the site's yield and which turbine class zoning allows. Only then is it worth paying for expert studies.
Next come the ecological surveys, which are often tied to growing seasons and therefore set the schedule. In parallel: the grid inquiry, securing the land, and coordination with the permitting authority.
05
Where projects get stuck
The most common delay comes from surveys started too late. Miss the species protection survey by one season and the project loses a year, even if every other document is ready.
The second issue is securing the land. New turbines need larger setbacks and different access roads, which leases from the 1990s rarely cover.
06Data sheet
Frequently asked questions
Does the new turbine have to stand in exactly the same spot?
Not necessarily, but it has to remain spatially connected to the existing installation. Moving it further away puts you back in the standard procedure.
How long does a repowering procedure take?
That depends on the surveys required. The ecological surveys are tied to the seasons and set the schedule.
07Contact
Get your turbine assessed.
We look at your turbine and tell you which option makes economic sense in your case.Planning & Repowering