01Hub height 60 mPlanning & repowering
Planning & Repowering
From site assessment to grid feed-in, delivered by our in-house planning team.
Scope of services
From idea to grid feed-in: our planning team supports new wind projects and repowering projects with technical and commercial expertise. We are currently running nine active planning projects.
- Site assessment & feasibility analysis
- Project development & permitting
- Technical design & grid planning
02Steps 1–6Planning & repowering
How a project runs.
Six steps from site assessment to commissioning. How long it takes depends on the permitting authority, the required expert reports and any objections.
Step 01 / 06
Site assessment
Wind resource, setback distances to buildings, nature conservation and zoning status. The result: whether the site is suitable, and for which turbine class.
Step 02 / 06
Feasibility
Yield forecast weighed against investment, operating costs and revenue assumptions. For repowering, also compared with continuing to run the existing turbines.
Step 03 / 06
Preliminary design and land rights
Turbine layout, access roads, crane pads and grid connection point. In parallel, agreements with landowners and the municipality.
Step 04 / 06
Permitting
Application under the BImSchG (Federal Immission Control Act) with the required studies on noise, shadow flicker and species protection.
For repowering under § 16b, the authority reviews only the changes compared with the existing turbines.
Step 05 / 06
Detailed design
Technical design, grid connection planning and coordination with the grid operator, tendering and contract award.
Step 06 / 06
Construction and commissioning
Construction supervision, commissioning, acceptance and handover to operations management, ours if you wish.
03Data sheet
Frequently asked questions.
What does repowering under § 16b BImSchG mean?
§ 16b of the BImSchG (Federal Immission Control Act) sets out a simplified permitting procedure for replacing existing wind turbines. The authority reviews only the changes compared with the existing turbines. That makes the process shorter than a new permit.
When does repowering pay off?
It depends on the quality of the site, the age and model of the existing turbine, and the zoning situation. We evaluate this in a site and feasibility analysis.
Background
Further reading.
7 min read
When an old turbine is replaced, the authority reviews only the changes compared with what's already there. This article covers what § 16b simplifies, which reviews remain, and where projects stall.
Repowering under § 16b BImSchG: How the process worksServices
More services.
- Wind turbine acquisition
- We buy your wind turbine and take over the operator's technical and legal obligations.
Turbine Acquisition - Service & maintenance
- Maintenance, inspection and repair by our own service crews. Any manufacturer, anywhere in Germany.
Service, Maintenance & Repair - Monitoring & remote control
- We monitor your turbine around the clock and step in remotely when faults occur.
Monitoring & Remote Control
04Contact
Get your site or repowering project assessed.
Tell us the location, the existing turbines and what you have in mind. We'll tell you which steps lie ahead and what a site assessment involves.
- Phone
- +49 000 0000000
- info@example.com
- Send a message
- Address
- Musterstraße 1, 12345 Musterstadt